Construction Schedule (Will be updated weekly)
Site | Start of Construction | Anticipated Lot Reopening | Alternative Parking |
33 Knightsbridge Lot | 1/17/23 | Pending | Not required at this point |
Lot 83 | 1/17/23 | Pending | Not required at this point |
Busch Lot 58A-58B Phase 1 | 2/20/23 | 6/7/23 |
Lots 51, 62, 65A-D, 67, 67A, 606, 603, 623, 58C, 602 |
RBHS Piscataway Lot B Phase 1 | 2/20/23 | 5/15/23 | Gravel Lot (next to Lot B) |
Livingston Lot 103 Phase 1 (northern half) | 3/06/23 | 6/08/23 | Lot 105 |
Busch Lot 63 | 3/13/23 | 8/11/23 | Not required at this point |
Busch Lot 67 Phase 1 (east two thirds) | 4/10/23 | 6/23/23 | Not required at this point |
Camden Lot C14 | 5/18/23 | 9/6/23 | Not required at this point |
Livingston Lot 101 | 5/24/23 | 8/14/23 | Lot 105, Yellow Lot |
Cook Lot 98B | 4/11/23 | 9/18/23 | Not required at this point |
Douglass Deck top level | 5/17/23 | 8/15/23 | |
Cook Lot 98A Phase 1 | 5/17/23 | 10/20/23 | Lot 97 |
College Ave Lots 26,27,30 | 5/22/23 | 8/15/23 | College Ave Parking Deck |
Busch Lots 65/65A/67A | 5/15/23 | 8/25/23 | Temporary Allen Hall Lot & Temporary Busch Yellow Lot |
Douglass Lot 79 and 79A | 5/17/23 | 8/25/23 | Lot 74A |
RBHS Piscataway Lot C Phase 2 | 5/16/23 | 9/29/23 | • Faculty and Staff: Lots 58, 58A, 58B, 58C, lot B and the Gravel Lot • Students: Lot B and the Gravel Lot |
Livingston Lot 103 Phase 2 (southern half) | 5/24/23 | 9/4/23 | Lot 105 |
Busch Lot 55 & 58 Phase 2 | 6/1/23 | 10/6/23 | Lots 51, 62, 65A-D, 67, 67A, 606, 603, 623, 58C, 602 |
Cook Lot 97 | 7/31/23 | 10/20/23 | Lot 98A |
RBHS Piscataway Lot A | 9/5/23 | 11/24/23 |
Faculty and Staff: Lots 58, 58A, 58B, 58C, Lot B and the Gravel Lot |